Several people have asked about the concept of a lower cost municipal WiFi system. The questions covered systems from very small areas to several hundred miles. To be honest; we haven’t yet deployed a multi-hundred mile Muni-WiFi system. As a Wireless Internet Service Provider (WISP), our smallest system is 15 clients and the largest system is about 270. I have designed and managed systems that handled up to 3000 users per day and supported about 30,000 users per year through pay per use servers. My designs are based on systems installed and deployed over the last several years that typically didn’t follow the standard cookie-cutter models. Since then I have engineered mesh systems for public safety and municipal utilities for video surveillance/analytics over 100 square miles, Major League spring Training baseball facilities, traffic systems, airports, city facilities, Point-to-Multipoint (PTMP) WISP systems, and PTP links up to 1Gbps. The proposal for a city-wide system is based on my experience and lessons learned with these systems and concepts.
A municipal wireless system is basically a bunch of hot spots connected through some type of wired or wireless backhaul system using a cluster of Access Points (APs). The system eventually funnels all traffic back to a central location which may utilize an authentication system to allow various users on the system. It’s pretty simple stuff with the devil in the details. However, the details are the difference between whether this system is financially and technically feasible or not. We are not going to cover that in one article. However, we will show how we developed and deployed different techniques over the last few years to create the foundation for a low cost, scalable Muni-Wireless system.
Before designing a system, determine the following basic issues:



  1. Determine the rules for deliverable product.



  2. Evaluate potential upgrade path for future growth



  3. Calculate costs/income if applicable
Let’s take the first case which is the simple idea of providing Internet in a building. I’m going to spend a little time on it because it’s a microcosm of a very large system. Consider it a miniature Muni-Wireless system in terms of number of users and the foundation for one of our industries. It’s also where we came up with the concept of eliminating fiber by using VDSL converters and using WDS for backhaul for AP to AP hopping. Later, we decided that Wireless Distribution System (WDS) was also preferable to mesh for our outdoor designs due to cost issues, the fact that mesh radios typically only connected to the radios before and after them meaning no change in the mesh structure, and that some of the mesh manufacturers weren’t using load balancing to determine mesh paths, only signal level and modulation.
Inside of a building or in a heavily populated area, there are two basic problems, density and connectivity. The inside of a building is basically a controlled environment. Outside in a populated area, you also have interference, but we will deal with that in a later article. We will also introduce a central server managed design based on these same concepts that will also greatly reduce the cost of in-building WiFi systems.
The first building we did, the Stratosphere Hotel in Las Vegas, was a pay system. Keep in mind that this was before WDS or mesh was any type of standard. At the time, we realized that we needed at least 50 APs to cover 2500 rooms on 24 floors with the ability to support about 200 users simultaneously. Due to building codes, all Ethernet cable for each radio would have to be in conduit. In addition, the cable runs from each AP would be well over 300’. One hallway alone was 270’ long. Conduit and cabling costs would run several hundred thousand dollars. The only existing asset we had was a few pairs of telephone wires in a vertical riser conduit that we could use. The vertical riser conduit was already full and there was no way additional cable could go in there.
The vertical asset problem was the easiest. We used Ethernet VDSL converters to push bandwidth from the data room several hundred feet away to a single Access Point to every other floor. These units support 10-15Mbps half-duplex for distances up to a mile across a twisted pair of wires with current versions supporting up to 100Mbps. VDSL also eliminated fiber which would have raised the cost significantly because of the fiber switches. That’s more than enough bandwidth for an 802.11b AP. Basically we traded $250,000-$500,000 worth of conduit work and fiber equipment for about $4000 worth of VDSL converters, a VDSL switch, and WDS which we discuss later. We eventually did the World Market Center in Las Vegas about a mile away with many of the same ideas.
Now that we had bandwidth on every other floor to 1 AP, the second problem was that the hallways were sequential meaning end-to-end. The hotel is in the shape of an S when seen by planes that fly over. That’s when we came up with the idea of using WDS hops from AP to AP while using the same radios in AP mode simultaneously. Since there were 2 radios in each AP, the WDS path went in one radio and out the other, thus minimizing the 1/n problem. There were 5 radios on every other floor. On each radio, we used custom directional antennas to aim down the hallways for greater range and better room penetration. At the time, the Vivato APs were the only units we could find that could support AP and WDS mode on the same radio simultaneously and were reasonably inexpensive at $350 per radio. Total cost of equipment for the entire installation was less than $40,000 with labor at about $10,000. It cost $3000-$4000 per month for bandwidth and tech support. We generated over a million dollars worth of revenue over the next 4 years from that system. The reason I use this example is because the techniques we learned became the foundation for almost every future system.
There was a book written called “All I really need to know I learned in Kindergarten” written by Robert Fulghum. We found that the Stratosphere was our Kindergarten. The VDSL units we used later saved another client $100,000 in their initial installation. The roaming spammers gave us the opportunity to test various methods of blocking them and handling high volumes of traffic. Hackers scanning through the system forced us to micromanage connectivity and to be proactive instead of reactive. The system was later upgraded to go from 200 simultaneous users to over 1000 over the next few years by simply adding more radios and VDSL entry points.
However, this is also where we learned the hard lesson as to what we believe caused many of the problems of future industry municipal systems. Our APs were 200mw. Our antennas were directional and approximately 12dBi. Laptops are 30-100mw. Because we couldn’t get approval to bring in more AP’s, there were some areas where clients could see us but couldn’t connect. They weren’t happy. Before I get hammered on why we didn’t have closer AP’s, the first radios that went in were at the end of the halls for coverage and backhaul. We were going to add additional radios later to cover poor signal areas but a change in management at the Stratosphere held up the second phase of the installation. Therefore, we had to live with hitting laptops at distances up to 135’ through several rooms for quite a while.
Nobody designs a Point-to-Point (PTP) system with 2 radios with dissimilar power levels, but that is how Municipal WiFi is implemented. Outdoor WiFi AP’s are typically 100mw to 1W. The end result is users thinking that if they saw bars on their computer, they should be able to connect. This differential caused huge problems for Muni-Wireless deployments with AP’s several hundred feet away trying to pick up laptop through brick, trees, and other obstacles. The patch for Muni-Wireless was to ask users to purchase high-power indoor units to fix that differential. That dampened enthusiasm and created additional interference issues. Another option would be a truck roll of an outdoor radio installed by a technician but that idea was never adopted by any of the bigger companies.
Adapting this idea to a Muni-Wireless model means that early 2.4GHz single radios systems should have been designed with the highest gain aesthetically pleasing antenna connected to APs set to about 100mw. That design would have been more productive, lower cost, and would have reduced the number of connection problems for clients. Ideally, the simplest, least expensive, and best AP would be about 20dBm with a 16dBi omni-antenna. This will deliver the longest range and best penetration bi-directionally with low power clients. Keep in mind I’m not addressing radios specifications, density, interference, or any of the higher tech ideas currently being deployed, just a basic single AP setup. Since we are after a cost effective system, that’s where our focus will be.
Muni-Wireless systems, like any other wireless network are made up of 3 parts:



  1. AP



  2. Transport



  3. Ingress/Egress
We are going to analyze each one of these for the cost/performance benefits of each phase over the next few articles and mix in some of our other installations to demonstrate real-world applications of these components in action. The goal is to demonstrate that it’s cost-effective for almost every city to have some type of system in place. Not every city needs a system that can do everything and with budgets where they are, it may not be realistic. However, defining the needs and expectations before the project will help the project stay within the financial scope of most cities.
With the Google offer demonstrating that hundreds of cities are interested in better bandwidth options, and this design capable of scaling up to 100Mbps per home, it’s evident that there is still a huge amount of interest in municipalities upgrading their infrastructure. Yes, fiber everywhere would be the ultimate option, but as an intermediate and realistic step, and considering Verizon is backing away from FIOS, not only can this system fill that need, but it can be built starting at about $3000 per square mile for a Muni-Wireless deployment. It can also be deployed as a PTMP system for less than $300 per AP location and $150 per household for more remote areas while integrating with the Muni-Wireless system later. The ultimate design is an integrated Muni-Wireless/PTMP structure.
What’s really funny is that cell phone companies that clearly can’t get enough bandwidth on a tower to support all the new smart phone applications, haven’t jumped on this concept nationwide to offload some of the bandwidth needs. In some cities, the cable companies are doing that. In others, the cell phone companies are supporting hot-spot integration. However, they can do 25 square miles with Gigabytes of capacity for less than it costs to put up 1 tower. That’s a discussion for a future article, however.

"Rory Conaway"